Illustrative case #1
Cost avoidance
COP 34M
Forgone returns
COP 101M
Total impact
COP 504M
Multiplier effect
On one of your projects, your steel supplier makes an offer that looks attractive at first glance: lock in the price for the next six months on 500 metric tons. The deal is COP 4,100/kg with a 1% early-payment discount, for an upfront outlay of COP 2,029.5 million. The project manager accepts.*
The reasoning behind the decision
Locking in the price with a 1% discount meant immediate savings of COP 20.5 million. A reasonable decision.
But it was made without knowing where the market was heading.
| Quantity | Price (COP) | Outlay (COP) |
|---|---|---|
| 500,000 kg | 4,100 | 2,029,500,000 |
Six months later, the cost-control team finds that steel prices have fallen COP 50/kg every month since the deal was signed. The seemingly conservative decision has led to a 3.4% cost overrun, or COP 67 million.
| Month | Quantity (kg) | Price (COP) | Total (COP) |
|---|---|---|---|
| 1 | 83,333 | 4,050 | 337,500,000 |
| 2 | 83,333 | 4,000 | 333,333,333 |
| 3 | 83,333 | 3,950 | 329,166,667 |
| 4 | 83,333 | 3,900 | 325,000,000 |
| 5 | 83,333 | 3,850 | 320,833,333 |
| 6 | 83,333 | 3,800 | 316,666,667 |
| Total | 1,962,500,000 |
3.4%
Cost overrun
Savings from paying upfront
The COP 20.5M is the 1% discount the supplier offered for paying for the steel upfront — the savings on the initial outlay. It partly offsets the overrun, so it comes off the total.
- Steel at the agreed price
- 500,000 kg × COP 4,100/kg = COP 2,050M
- Early-payment discount (1%)
- COP 2,050M × 1% = COP 20.5M
- Upfront outlay
- COP 2,050M – COP 20.5M = COP 2,029.5M
8%
Annual opportunity cost
Total impact
COP 67M + COP 34M = COP 101M
The true opportunity cost
That COP 2,029.5M could have been earning returns while most of the material wasn’t yet needed on site.
Assuming an 8% annual return (a trust company’s money market fund), holding on to the funds instead of paying in advance would have earned more than in interest.
Add those forgone returns to the overrun from falling prices, and the real cost climbs to COP 101M — a 5% premium on the steel.
COP 504M
Multiplier effect
If similar decisions, all made with the best of intentions, had been repeated across five of your projects, they would have cost the company more than COP 504 million over six months.
Forgone returns, month by month
Capital invested at 8% EAR and withdrawn in six equal installments at the start of each month. Figures in millions of Colombian pesos (COP).
| Month | Opening balance | Drawn at start | Invested balance | Monthly interest | Closing balance |
|---|---|---|---|---|---|
| 1 | 2,050.0 | 341.7 | 1,708.3 | 11.0 | 1,719.3 |
| 2 | 1,719.3 | 341.7 | 1,377.7 | 8.9 | 1,386.5 |
| 3 | 1,386.5 | 341.7 | 1,044.9 | 6.7 | 1,051.6 |
| 4 | 1,051.6 | 341.7 | 709.9 | 4.6 | 714.5 |
| 5 | 714.5 | 341.7 | 372.8 | 2.4 | 375.2 |
| 6 | 375.2 | 341.7 | 33.5 | 0.2 | 33.8 |
| Total | 2,050.0 | 33.8 |
Looking back: What could have gone differently?
Now imagine a different scenario. Before giving the supplier an answer, your team takes one crucial step: checking the Supply Intelligence module.
Instant insight
Within minutes, they would have a complete, well-grounded picture of the market, not just an opinion.
Visual analysis
Charts that show the material’s price history and, more importantly, where its price is projected to go.
Qualitative context
In-depth analysis that puts supply and demand pressures in context and pinpoints bearish or bullish trends.
With this information, they would have seen that the “safe price” they were being offered was really an unnecessary premium, given where the market was actually heading.
And in a rising market?
Conversely, had steel risen COP 50/kg each month, the decision would have saved the project nearly COP 108,000,000.
With Onion, that purchase would have been a decision, not a gamble.
What would this analysis look like for your projects and volumes?